Delays Expected Next Week During Rt. 13 Resurfacing Project

GREENE COUNTY, Mo. - A resurfacing project beginning next week will close down lanes on Rt. 13 between I-44 in Springfield and the Greene/Polk county line south of Bolivar.
GREENE COUNTY, Mo. - A resurfacing project beginning next week will close down lanes on Rt. 13 between I-44 in Springfield and the Greene/Polk county line south of Bolivar.

Drivers can expect nighttime lane closings beginning the week of July 28 as contractor crews work to resurface the northbound and southbound lanes of Rt. 13 and shoulders of the highway.

Crews expect to start on the north end of the project at the Greene/Polk county line in an effort to avoid Ozark Empire Fair traffic while the fair is underway, according to MoDOT.

Crews may decide to work during daytime hours when working at the north end between Greene County Rt. WW and the Greene/Polk county line.

Project Background

Prime Contractor: Blevins Asphalt Construction Co., Mt. Vernon

Completion Date: November 1, 2014

Construction Cost: $4.8 million